CLIPS Executive RCLL

Task

Fetch a base from the base station.

  • Create a goal to fetch the base.
  • Call the PDDL Planner to create a plan for the goal.
  • Execute the plan.

Branches to use

  • fawkes-robotino: common/clips-executive-rcll
  • fawkes core: common/current-clips-executive-rcll

You will need to rebuild after updating your branches.

How to run

  • Run the simulation as before with ./gazsim.bash -x start -r -k -n 1 -t
  • Select the team
  • Start setup
  • Load the clips-executive meta plugin: ./ffplugin -r localhost:1921 -l gazsim-meta-clips-exec
  • Switch to production

Update: Instead of running the simulation and loading the plugin separately, you can also directly start the simulation with the executive: ./gazsim.bash -x start -r -k -n 1 -t -a (note the -a)

Hints

  • The agent now needs to communicate with the refbox. After you loaded the clips-executive, the robot should appear in the refbox.
  • To fetch a product from the base station, the agent first needs to send a prepare message, which is modelled as plan-action prepare-bs . The action sends the message and waits for the message to be processed. The machine state should switch from IDLE to PROCESSING and then to READY-AT-OUTPUT .
  • The world model is stored in wm-facts. The information in the world model comes from the refbox or from action effects. Relevant wm-facts are synced to domain-facts automatically.
  • domain-predicates now have an optional sensed property. If an action has a sensed predicate as effect, the effect is not applied as normal, but instead the execution waits until it can sense the predicate. Only after sensing the effect, the action is set to FINAL .
  • Part of the infrastructure code is still work in progress. In particular, you may note the following issues:
    • The planner returns an invalid plan or says that the plan is not solvable. This may happen if the planner did not have all domain facts during planning. Re-planning usually solves the problem.
    • wm-facts and domain-facts are not in sync.
    • After a prepare-bs , the domain-fact for the mps state is not READY-AT-OUTPUT even if the refbox says that the MPS is READY-AT-OUTPUT .

We are working on fixing these issues.